| Name of Project | |
| Mussaib Gas Turbine Plant Tank Farm & Associated Piping Reconstruction. | |
| Description Of Services | |
| Supply technical management staff, craft labor, materials, and equipment necessary to completely refurbish and reconstruct a portion of the Tank Farm associated with the Mussaib LM6000 Gas Plant. | |
![]() |
![]() |
| Name of Project | |
| Baghdad South / Qudas Power Station 2007 Maintenance Overhauls. | |
| Description Of Services | |
| Four years of operation & maintenance and included all due inspection for 4 GE Frame 917/E Units. Supply technical management staff, craft labor, materials, capital parts (as needed) and equipment necessary to perform various Hot Gas Path Inspections, Combustion Inspections, Qudas #2 Turbine & Compressor Rotor Repairs, and complete commissioning and reliability testing of Frame 9E Gas Turbines located at the Baghdad South Gas Plant and the Qudas Power Station. | |
![]() |
![]() |
| Name of Project | |
| Mullah Gas Turbine Overhauls and Refurbishments. | |
| Description Of Services | |
| Complete refurbishment, upgrade and overhaul of 4 GE Frame 5P and 5 GE Frame 6 Units. Supply technical management staff, craft labor, materials, capital parts (as needed) and equipment necessary to complete major overhaul and refurbishment activities on Frame 6B Gas Turbines and Auxiliaries to include Main Transformers, Electrical Distribution, and Relaying. | |
![]() |
![]() |
| Name of Project | |
| Two Siemens Westinghouse 501F gas turbines. | |
| Description Of Services | |
| Two SiemensWestinghouse 501F gas turbines with Cerrey 3 pressure HRSGs and a 160MW Siemens steam turbine. Final construction, commissioning and initial operation supervision contracted to Wamar. | |
![]() |